Monday, May 24, 2010

Log 5/24

Task Started: Water

Tasks Completed: Water

Tasks to be Completed:

Friday, May 14, 2010

Log 5/14

Task Started: Ocean Bottom

Tasks Completed: Ocean Bottom

Tasks to be Completed: Making Water Line.

Wednesday, May 5, 2010

Log 5/5

Task Started: Ocean Bottom


Tasks Completed: Made cardboard box
Tasks to be Completed: Making Water and Ocean Bottom.

Wednesday, April 21, 2010

Log 4/21

Task Started: Boom
Tasks Completed: Completed attaching boom

Tasks to be Completed: Making Water and Ocean Bottom.

Friday, April 16, 2010

Calendar for Fourth Marking Period

Due Dates:
4/30 Testing
5/5 Formal Progress Update Presentation, Weblog
5/20 Exhibition Night
5/27 Mentor Contacts
5/28 Log Sheet, Self Evaluation
6/8 Final Exam Journal Article

Schedule:
4/15-4/23 Finish Model
4/16 Schedule meeting with Mr.Danko for testing
4/24-4/30 Work on testing sheet
5/1-5/5 Prepare for Formal Progress Update Presentation and Weblog
5/10-5/20 Prepare for Exhibition Night
5/26-5/27 Mentor Contact Sheet
5/26-5/28 Self Evaluation
6/3-6/8 Final Exam Journal Article

Mentor Contact will be kept throughout
Logs will be updated two times per week

Wednesday, April 14, 2010

4/14

Task Started: Painting. Boom


Tasks Completed: Painted Concrete and Lumber. Completed model of boom
Tasks to be Completed: Making Water and Ocean Bottom. Painting. Plexyglass container

Wednesday, March 17, 2010

Log 3/17

Task Started: Tapered Dowels. Glued Decking Surface


Tasks Completed: Tapered Dowels. Glued Decking Surface.

Tasks to be Completed: Construction. Making Water and Ocean Bottom. Attaching Pilings

Monday, March 15, 2010

Friday, March 5, 2010

Log 3/5

Task Started: Gathered Materials. Cut blocks of wood and dowels to size. Sanded Dowels


Tasks Completed: Gathered Materials. Cut blocks of wood and dowels to size.
Tasks to be Completed: Continue detailing marina layout. Call company for boom sample. Construction

Wednesday, February 24, 2010

Log 2/24

Task Started: Press Release, Inserting Wind Turbines, Inserted Moorings, Inserting Electrical Lines


Tasks Completed: Completed Inserting Wind Turbines, Inserted Moorings, Inserting Electrical Lines



Tasks to be Completed: Continue detailing marina layout. Call company for boom sample. Add depth contour lines. Press Release

Wednesday, February 17, 2010

Log 2/17

Task Started: Inserting Gasoline Lines and Boom Placement


Tasks Completed: Completed Inserting Gasoline Lines and Boom Placement

Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample. Add depth contour lines. Insert electrical lines

Friday, February 12, 2010

Log 2/12

Task Started: Inserting Electrical, Lighting, and Freshwater
Tasks Completed: Completed Inserting Freshwater

Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample. Add depth contour lines. Insert electrical lines

Friday, February 5, 2010

Log 2/5

Task Started: Inserting Fire Extinguishers

Tasks Completed: Completed Inserting Fire Extinguishers

Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample. Add depth contour lines.

Wednesday, February 3, 2010

Log 2/3

Task Started: Inserting Boat Slips


Tasks Completed: Completed inserting boat slips. Calandar
Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample. Add depth contour lines.

Monday, February 1, 2010

Calandar for Third Marking Period

Due Dates:


2/29 Press Release

3/4 Construction Assignment and Assessment

3/11 Formal Progress Update Presentation, Log Sheet

3/17 Mentor Contacts

Schedule:

2/1-2/5 Insert Pilings and Catwalks

2/8-2/12 Insert Depth Markers

2/16-2/19 Insert Miscelaneous Items (Lights, Fire Extinguishers, Electrical Outlets, Wind Turbines, Gasoline, Freshwater Access)

2/22-2/26 Work on Press Release

3/1 Schedule meeting with Mr. Danko to test design

3/1-3/2 Complete Site Plan

3/3 Prepare for Formal Progress Update Presentation


Mentor Contact will be kept throughout

Logs will be updated two times per week

Friday, January 29, 2010

Log 1/29

Task Started: Continued detailing marina slips
Tasks Completed: N/A

Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample. Calendar. Add boat slips. Add depth contour lines.

Friday, January 22, 2010

Log 1/22

Task Started: Breakwater design.


Tasks Completed: Breakwater Design. Modified developmental work

Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample.

Wednesday, January 20, 2010

Log 1/20

Task Started: Breakwater design.


Tasks Completed: Formal Report Updated. Mentor Contacts

Tasks to be Completed: Complete calculation of number of wind turbines. Complete drawing of breakwater. Continue detailing marina layout. Call company for boom sample. Modify Developmental Work.

Monday, January 11, 2010

Developmental Work

Layout


Strucutal Plan





Boom Attachment






Materials List

1 Oil absorbent polypropylene fabric boom
   Quantity: 40
   Size: 8” diameter x 20’
   Remarks: Cleans water of petroleum based oils

2 Piling Cap
   Quantity: 385
   Size: 10’x2’x1’
   Remarks: Made from reinforced concrete

3 Trex Decking Material
   Quantity: 13110
   Size: 10’x6”x2”
   Remarks: Decking Material

4 Pilings
   Quantity: 754
   Size: t-1’, b-8”x 16’
   Remarks: Made from reinforced concrete

5 WhisprWave Floating Breakwater
   Quantity: 1
   Size: 1600’ long

Wednesday, January 6, 2010

Log 1/06

Task Started: Modifying marina layout. Stemm Report


Tasks Completed: Stemm Report
Tasks to be Completed: Complete calculation of number of wind turbines. Complete drawing of breakwater. Continue detailing marina layout. Call company for boom sample. Modify Developmental Work. Mentor Contacts