Wednesday, February 24, 2010

Log 2/24

Task Started: Press Release, Inserting Wind Turbines, Inserted Moorings, Inserting Electrical Lines


Tasks Completed: Completed Inserting Wind Turbines, Inserted Moorings, Inserting Electrical Lines



Tasks to be Completed: Continue detailing marina layout. Call company for boom sample. Add depth contour lines. Press Release

Wednesday, February 17, 2010

Log 2/17

Task Started: Inserting Gasoline Lines and Boom Placement


Tasks Completed: Completed Inserting Gasoline Lines and Boom Placement

Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample. Add depth contour lines. Insert electrical lines

Friday, February 12, 2010

Log 2/12

Task Started: Inserting Electrical, Lighting, and Freshwater
Tasks Completed: Completed Inserting Freshwater

Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample. Add depth contour lines. Insert electrical lines

Friday, February 5, 2010

Log 2/5

Task Started: Inserting Fire Extinguishers

Tasks Completed: Completed Inserting Fire Extinguishers

Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample. Add depth contour lines.

Wednesday, February 3, 2010

Log 2/3

Task Started: Inserting Boat Slips


Tasks Completed: Completed inserting boat slips. Calandar
Tasks to be Completed: Complete calculation of number of wind turbines. Continue detailing marina layout. Call company for boom sample. Add depth contour lines.

Monday, February 1, 2010

Calandar for Third Marking Period

Due Dates:


2/29 Press Release

3/4 Construction Assignment and Assessment

3/11 Formal Progress Update Presentation, Log Sheet

3/17 Mentor Contacts

Schedule:

2/1-2/5 Insert Pilings and Catwalks

2/8-2/12 Insert Depth Markers

2/16-2/19 Insert Miscelaneous Items (Lights, Fire Extinguishers, Electrical Outlets, Wind Turbines, Gasoline, Freshwater Access)

2/22-2/26 Work on Press Release

3/1 Schedule meeting with Mr. Danko to test design

3/1-3/2 Complete Site Plan

3/3 Prepare for Formal Progress Update Presentation


Mentor Contact will be kept throughout

Logs will be updated two times per week