Due Dates:
2/29 Press Release
3/4 Construction Assignment and Assessment
3/11 Formal Progress Update Presentation, Log Sheet
3/17 Mentor Contacts
Schedule:
2/1-2/5 Insert Pilings and Catwalks
2/8-2/12 Insert Depth Markers
2/16-2/19 Insert Miscelaneous Items (Lights, Fire Extinguishers, Electrical Outlets, Wind Turbines, Gasoline, Freshwater Access)
2/22-2/26 Work on Press Release
3/1 Schedule meeting with Mr. Danko to test design
3/1-3/2 Complete Site Plan
3/3 Prepare for Formal Progress Update Presentation
Mentor Contact will be kept throughout
Logs will be updated two times per week