Task Started: Modifying marina layout
Tasks Completed: Completed structure design.
Tasks to be Completed: Continue calculation of number of wind turbines. Continue modifing marina layout. Start and complete mooring design. Start and complete drawing of breakwater. Continue detailing marina layout. Call company for boom sample.
Friday, December 11, 2009
Wednesday, December 9, 2009
Log 12/9
Task Started: Developmental Work on oil absorbent polyproplene fabric boom attachment.
Tasks Completed: Met with Mr. Danko to review work. Completed basic structure design. Met with team to discuss modifications. Contacted bulkheading company for dimensions.
Tasks to be Completed: Continue calculation of number of wind turbines. Modify marina layout. Complete detailed structure design. Start and complete mooring design. Start and complete drawing of breakwater. Complete oil absorbent polyproplene fabric boom design. Continue detailing marina layout. Call company for boom sample.
Tasks Completed: Met with Mr. Danko to review work. Completed basic structure design. Met with team to discuss modifications. Contacted bulkheading company for dimensions.
Tasks to be Completed: Continue calculation of number of wind turbines. Modify marina layout. Complete detailed structure design. Start and complete mooring design. Start and complete drawing of breakwater. Complete oil absorbent polyproplene fabric boom design. Continue detailing marina layout. Call company for boom sample.
Thursday, December 3, 2009
Log 12/3
Task Started: Started Developmental Work on structuring
Tasks Completed: Emailed Mr. Danko to schedule meeting to review work. Finished Bid Process. Finished modifying marina layout. Completed basic structure design. Met with team to discuss model. Finished calculations for model.
Tasks to be Completed: Continue calculation of number of wind turbines. Complete detailed structure design. Start and complete mooring design. Start and complete drawing of breakwater. Complete oil absorbent polyproplene fabric boom design. Continue detailing marina layout. Call company for boom sample.
Tasks Completed: Emailed Mr. Danko to schedule meeting to review work. Finished Bid Process. Finished modifying marina layout. Completed basic structure design. Met with team to discuss model. Finished calculations for model.
Tasks to be Completed: Continue calculation of number of wind turbines. Complete detailed structure design. Start and complete mooring design. Start and complete drawing of breakwater. Complete oil absorbent polyproplene fabric boom design. Continue detailing marina layout. Call company for boom sample.
Wednesday, November 18, 2009
Calendar for Second Marking Period
Due Dates:
11/25 Bid Process
12/22 Developmental Work
1/5 Math and Science Analysis, Mentor Contacts
1/11 Formal Progress Update Presentation, Log Sheet
Schedule:
11/15-11/25 Work on Bid Process
11/26-12/22 Work on Developmental Work
12/23-1/5 Work on Math and Science Analysis
1/6-1/11 Prepare for Formal Progress Update Presentation
Mentor Contact will be kept throughout
Logs will be updated two times per week
11/25 Bid Process
12/22 Developmental Work
1/5 Math and Science Analysis, Mentor Contacts
1/11 Formal Progress Update Presentation, Log Sheet
Schedule:
11/15-11/25 Work on Bid Process
11/26-12/22 Work on Developmental Work
12/23-1/5 Work on Math and Science Analysis
1/6-1/11 Prepare for Formal Progress Update Presentation
Mentor Contact will be kept throughout
Logs will be updated two times per week
Tuesday, November 17, 2009
Log 11/17
Task Started: Continued modifying design.
Tasks Completed: Emailed and called Mr. Danko to change time for meeting to review work. Reviewed Green Marina Guidlines.
Tasks to be Completed: Continue calculation of number of wind turbines. Finish modifying design. Make calendar
Tasks Completed: Emailed and called Mr. Danko to change time for meeting to review work. Reviewed Green Marina Guidlines.
Tasks to be Completed: Continue calculation of number of wind turbines. Finish modifying design. Make calendar
Friday, November 13, 2009
Log 11/13
Task Started: Started modifying design
Tasks Completed: emailed Mr. Danko to confirm a meeting to review work
Tasks to be Completed: Continue calculation of number of wind turbines. Finish modifying design.
Tasks Completed: emailed Mr. Danko to confirm a meeting to review work
Tasks to be Completed: Continue calculation of number of wind turbines. Finish modifying design.
Wednesday, November 11, 2009
Log 11/11
Task Started: Researched marine inverters. started researching information to aid in the process of calculating the number of wind turbines needed to power 400 boats.
Tasks Completed: emailed mentor to discuss the process of calculating the number of wind turbines. Discussion with Cheryl McDonald about floating breakwaters and sediment build-up
Tasks to be Completed: Find more information needed in calculation. Start calculation.
Tasks Completed: emailed mentor to discuss the process of calculating the number of wind turbines. Discussion with Cheryl McDonald about floating breakwaters and sediment build-up
Tasks to be Completed: Find more information needed in calculation. Start calculation.
Subscribe to:
Posts (Atom)