Monday, January 11, 2010

Developmental Work

Layout


Strucutal Plan





Boom Attachment






Materials List

1 Oil absorbent polypropylene fabric boom
   Quantity: 40
   Size: 8” diameter x 20’
   Remarks: Cleans water of petroleum based oils

2 Piling Cap
   Quantity: 385
   Size: 10’x2’x1’
   Remarks: Made from reinforced concrete

3 Trex Decking Material
   Quantity: 13110
   Size: 10’x6”x2”
   Remarks: Decking Material

4 Pilings
   Quantity: 754
   Size: t-1’, b-8”x 16’
   Remarks: Made from reinforced concrete

5 WhisprWave Floating Breakwater
   Quantity: 1
   Size: 1600’ long

Wednesday, January 6, 2010

Log 1/06

Task Started: Modifying marina layout. Stemm Report


Tasks Completed: Stemm Report
Tasks to be Completed: Complete calculation of number of wind turbines. Complete drawing of breakwater. Continue detailing marina layout. Call company for boom sample. Modify Developmental Work. Mentor Contacts

Friday, December 18, 2009

Log 12/18

Task Started: Modifying marina layout. Isometric boom design
Tasks Completed: Completed isometric boom design.

Tasks to be Completed: Complete calculation of number of wind turbines. Complete modifing marina layout. Complete mooring design. Complete drawing of breakwater. Continue detailing marina layout. Call company for boom sample. Complete electrical and gasoline plan. Complete plan of proceedures.

Wednesday, December 16, 2009

Log 12/16

Task Started: Modifying marina layout. Isometric structure design.


Tasks Completed: Completed isometric structure design.

Tasks to be Completed: Complete calculation of number of wind turbines. Complete modifing marina layout. Complete mooring design. Complete drawing of breakwater. Continue detailing marina layout. Call company for boom sample. Complete electrical and gasoline plan. Complete isometric boom design. Complete plan of proceedures

Friday, December 11, 2009

Log 12/11

Task Started: Modifying marina layout


Tasks Completed: Completed structure design.


Tasks to be Completed: Continue calculation of number of wind turbines. Continue modifing marina layout. Start and complete mooring design. Start and complete drawing of breakwater. Continue detailing marina layout. Call company for boom sample.

Wednesday, December 9, 2009

Log 12/9

Task Started: Developmental Work on oil absorbent polyproplene fabric boom attachment.


Tasks Completed: Met with Mr. Danko to review work. Completed basic structure design. Met with team to discuss modifications. Contacted bulkheading company for dimensions.

Tasks to be Completed: Continue calculation of number of wind turbines. Modify marina layout. Complete detailed structure design. Start and complete mooring design. Start and complete drawing of breakwater. Complete oil absorbent polyproplene fabric boom design. Continue detailing marina layout. Call company for boom sample.

Thursday, December 3, 2009

Log 12/3

Task Started: Started Developmental Work on structuring

Tasks Completed: Emailed Mr. Danko to schedule meeting to review work. Finished Bid Process. Finished modifying marina layout. Completed basic structure design. Met with team to discuss model. Finished calculations for model.

Tasks to be Completed: Continue calculation of number of wind turbines. Complete detailed structure design. Start and complete mooring design. Start and complete drawing of breakwater. Complete oil absorbent polyproplene fabric boom design. Continue detailing marina layout. Call company for boom sample.